|
1
|
- Dr. Walid H. Shayya
- School of Agriculture & Natural Resources
- Morrisville State College
Last Updated on May 7, 2007
|
|
2
|
- The free-stall Dairy Complex at Morrisville State College was built in
2001.
|
|
3
|
- The free-stall Dairy Complex at Morrisville State College was built in
2001 with a
- free-stall barn that houses 200 milking cows, and
- a double-eight herringbone, rapid exit milking parlor equipped with an
automatic cow identification system.
|
|
4
|
- The free-stall Dairy Complex is located about a mile southwest of the
center of campus.
|
|
5
|
- Several exciting new additions to the dairy complex were made over the
past three years:
- Two barns for heifers, dry cows, and bred heifers were constructed in
2004.
- Milking cows housing facilities were consolidated on campus with the
60-cow tie-stall barn being closed and the animals moved to the Dairy
Complex.
- Two calf barn constructed as student instruction projects (one
constructed in 2004 and a second scheduled for completion in 2007).
- A show barn built as a student instruction project in 2006.
- A plug-flow anaerobic digester and an equipment building constructed in
2006.
- What was missing (until recently) from the manure management
perspective?
- The Dairy Complex did not include long-term manure storage (a
three-month storage tank was constructed in late 2006).
- Only a 3-day manure storage tank was built with the dairy complex.
- The daily-haul method is used to spread manure on college fields
(should no longer be followed starting from early 2007).
|
|
6
|
- The Dairy Complex is a teaching facility where technical practices will
emulate commercial dairy operations.
- Facility intended to train the students in the area of feeding, herd
health, dairy herd management, and manure and nutrient management.
- Practical research and demonstration was also envisioned with the
facility to address questions relative to dairy herd and animal waste
management.
|
|
7
|
- A feasibility study funded by the NYS Department of Agriculture and
Markets was initiated in 2000 to select an environmentally-sound and
economically-feasible waste management system for the Dairy Complex at
Morrisville State College.
- Anaerobic digestion was found to be a feasible and a promising method
for treating the dairy manure and other organic waste generated on
campus!
|
|
8
|
- Treatment of organic waste.
- Odor control.
- Biogas generation and energy production.
- Environmental benefits.
- Economic benefits.
- Potential for using the anaerobic digester as a demonstration project to
New York farmers and dairy producers.
- College’s mission of educating students and providing them with hands-on
experiences using state-of-the-art facilities.
|
|
9
|
- A proposal was submitted to NYSERDA in 2001 to have the project funded
on cost-share basis ($300,000 were awarded).
- Through collaborations with NYSERDA and NYPA, another $155,000 were
secured from the NYS Department of Agriculture and Markets.
- Another $198,000 were secured from Federal sources through Congressman
McHugh’s office (congressional earmarked funds administered by the DOE
Golden Office).
|
|
10
|
- Funding was provided to build the digester and conduct some applied
research on the system.
- Dave Palmer of Cow Power was hired in 2002 (through a Request for
Qualifications) to design the system.
- The first design was completed in 2003 and a competitive bidding process
for a contractor was initiated.
- Two additional revisions to the design and bidding processes had to be
followed in 2004 and 2005 before the current contractor, Paul Yaman
Construction, was awarded the contract in 2005 as the lowest bidder.
|
|
11
|
- Design calls for a dual-chamber, hard-top, plug-flow digester
(90.67x37x11.67”).
- Digester to handle manure from an equivalent of 400 milking cows.
- Manure handled by the digester is to fit within the CAFO plan for the
dairy operation developed by the Dr. Adam Khan, an Agronomist at MSC and
a certified AEM Planner.
|
|
12
|
- The construction contract was awarded to Paul Yaman Construction in
early August and the contractor mobilized to the site on August 3, 2005.
- Site preparation and excavation for the construction of the two-sided
tank was completed in early August, 2005.
|
|
13
|
|
|
14
|
|
|
15
|
- The forms were then done and the concrete for the digester floor and
walls was poured in late August, early September, 2005.
|
|
16
|
|
|
17
|
|
|
18
|
|
|
19
|
|
|
20
|
|
|
21
|
|
|
22
|
|
|
23
|
|
|
24
|
|
|
25
|
|
|
26
|
|
|
27
|
|
|
28
|
|
|
29
|
|
|
30
|
|
|
31
|
|
|
32
|
- The pre-cast concrete planks were installed on the 10th of October,
2005. The joints of the concrete
planks were then sealed and a 4”-concrete top coat applied.
- The heat loop inside each of the two chambers of the digester as well as
the heat exchangers inside the grit chamber of each side of the digester
were also installed in early October, 2005.
|
|
33
|
|
|
34
|
|
|
35
|
|
|
36
|
|
|
37
|
|
|
38
|
|
|
39
|
|
|
40
|
|
|
41
|
|
|
42
|
|
|
43
|
|
|
44
|
|
|
45
|
|
|
46
|
|
|
47
|
|
|
48
|
|
|
49
|
|
|
50
|
|
|
51
|
|
|
52
|
|
|
53
|
|
|
54
|
|
|
55
|
- The outside of the walls of the digester as well as the digester top
were insulated using polyurethane and a top black coat applied to
protect the insulation from UV light damage.
- The back-fill and packing of the soil behind the outside walls of the
digester was started at the end of October.
- The inside of the top of the digester was finished and coal tar epoxy
coating was applied in early November to seal the insides of the two
chambers of the digester.
|
|
56
|
|
|
57
|
|
|
58
|
|
|
59
|
|
|
60
|
|
|
61
|
- The outlet bay of the digester was formed and poured in November, 2005.
- The back-fill and packing of the soil behind the outside walls of the
digester as well as the area around the CHP building was completed
during the week of the 26th of November.
|
|
62
|
|
|
63
|
|
|
64
|
|
|
65
|
|
|
66
|
|
|
67
|
|
|
68
|
|
|
69
|
|
|
70
|
|
|
71
|
|
|
72
|
- The installation of insulated steel pipes for heated water that connect
the CHP to the influent side of the digester was completed and
pressure-tested at the end of November, 2005.
- More back-filling and packing of the soil behind the outside walls of
the digester as well as the area around the CHP building was completed.
|
|
73
|
|
|
74
|
|
|
75
|
|
|
76
|
|
|
77
|
|
|
78
|
|
|
79
|
|
|
80
|
|
|
81
|
|
|
82
|
|
|
83
|
|
|
84
|
|
|
85
|
|
|
86
|
|
|
87
|
|
|
88
|
|
|
89
|
|
|
90
|
- A PVC pipe was installed to connect the manure storage tank to the
digester so that a pump can be used to move the influent to the
digester.
|
|
91
|
|
|
92
|
|
|
93
|
|
|
94
|
|
|
95
|
- Work on the CHP building continued.
- Several pieces of equipment were assembled in CHP building.
|
|
96
|
|
|
97
|
|
|
98
|
|
|
99
|
|
|
100
|
|
|
101
|
|
|
102
|
|
|
103
|
|
|
104
|
- The engine/generator set was assembled by Martin Machinery (the supplier
of the CHP system and heat exchangers, located in Latham, Missouri).
|
|
105
|
|
|
106
|
|
|
107
|
|
|
108
|
- The equipment/generator set equipment were then delivered to the site on
several skids.
|
|
109
|
|
|
110
|
|
|
111
|
- The existing 3-day storage was subdivided into two compartments.
- The subdivision of the tank was accomplished through an 8” concrete
dividing wall that was formed and poured.
- The profile of the existing manure storage tank allowed for its
subdivision without the need to stop the flow of scraped manure from
the barn and wash water from the milking parlor.
|
|
112
|
|
|
113
|
|
|
114
|
|
|
115
|
- A bypass of the footbath was constructed. The bypass involved the installation
of 6”-PVC pipe (used to intersect the existing drain pipe in the dairy
barn) that connected to the 36” effluent pipe from the digester (located
between the CHP building and the digester), thereby completely bypassing
the system.
- The 36” effluent pipe that was already installed along the SW side of
the digester was extended to reach the new effluent compartment of the
existing storage tank.
|
|
116
|
- Arrangements of the various mechanical and electrical components of the
system were made within the CHP building.
- The flare system was installed and the biogas lines were connected to
the CHP building during the middle part of May, 2006.
|
|
117
|
|
|
118
|
|
|
119
|
|
|
120
|
|
|
121
|
|
|
122
|
|
|
123
|
|
|
124
|
|
|
125
|
- Control wiring was connected to several equipments in the equipment
building.
- The exhaust from the internal combustion engine was installed along with
radiator set to dump excess heat from the engine.
|
|
126
|
|
|
127
|
|
|
128
|
|
|
129
|
|
|
130
|
|
|
131
|
- The grading of the area around the digester and existing manure pit and
the spreading of a layer of top soil over the entire disturbed
construction site (including the digester) followed by seeding and
mulching.
|
|
132
|
|
|
133
|
|
|
134
|
|
|
135
|
|
|
136
|
|
|
137
|
|
|
138
|
|
|
139
|
|
|
140
|
- A polyurethane layer and a poly-urea coating were applied to the inside
of the digester on the 29th of August, 2006.
- Applications were made to the ceiling of the digester as well as the
inside walls of both chambers to a level of about a couple of feet
below the liquid line in the tank.
- Applications were intended to provide a gas-tight digester.
|
|
141
|
|
|
142
|
- The digester was filled with water and pressure-tested for leaks. The tests resulted in a drop of less
than 0.15 inches of H2O column per hour (<0.15 in/hr), an
acceptable criterion which is below the 0.25 in/hr threshold set within
the design manual as the upper limit for an acceptable test.
|
|
143
|
- A propane tank was installed and connected to the boiler that will be
used for heating the digester during startup.
- A new website on alternative energy projects at Morrisville State
College was developed and posted to the web around the 18th
of September, 2006. The website
focuses primarily on the methane digester and the 10-kW wind turbine
projects.
|
|
144
|
|
|
145
|
|
|
146
|
|
|
147
|
- The aluminum covers at the effluent side of the digester and the access
ports were installed.
- The process of digester startup was initiated on the 21st of
September, 2006. Within a period
of 10 days, the influent that was pumped into the grit chamber of the SW
side of digester reached about few inches below the baffle on the
effluent side of the digester.
- Since the permanent pump was not installed yet, a temporary six-inch
pipe was installed to pump the influent using an existing
tractor-driven pump.
|
|
148
|
|
|
149
|
|
|
150
|
|
|
151
|
- A Sampling, Testing, and Evaluation Plan (STEP) on the project was
prepared and discussed during a
Project Advisory Group (PAG) meeting held at the Dairy Complex on Friday
– September 22, 2006.
|
|
152
|
- One setback on the project involved the digging up of the heat-loop
valves on the influent side of the digester to have those replaced after
a leak was discovered.
- The heating of the digester was started on October 11, 2006.
- The boiler was run at a temperature of about 100ºF until October 23,
2006
- A water leak was discovered in the system which required the cessation
of heating of the SW side of the digester.
- It took about a week to fix the problem!
|
|
153
|
|
|
154
|
|
|
155
|
|
|
156
|
|
|
157
|
|
|
158
|
|
|
159
|
- A total of 100 lb of inoculant was added on the 1st of
November (2006) at four locations within the SW side of the digester.
Within six days of the application of PIM, the biogas pressure in the
digester developed from about 0.5 inches of water column to 6.6 inches
as measured on November 7, 2006.
- The gas pressure in the digester dropped to less than 0.5 inches on the
9th of November following the increase of temperature in the
digester to an average of 108ºF.
This was the result of attempting to find the right temperature
setting on the boiler to provide an optimum temperature of 98ºF within
the digester. Within a couple of
days of attempting to address this problem, the temperature in the
digester returned to the 96-103ºF range and the pressure increased again
to about 6 inches as measured on November 15, 2006.
|
|
160
|
|
|
161
|
|
|
162
|
- The concentration of CO2 in the generated biogas was measured
at 55-60% on the 15th of November (2006).
- The process of installing an electric pump to load manure into the
digester was completed on November 28, 2006. The process involved
- the installation of an electric control box,
- the fabrication and installation of a platform, and
- the actual installation of the pump which took place after the influent
compartment of the existing manure storage tank was emptied and cleaned
during the morning of November 28, 2006.
|
|
163
|
|
|
164
|
|
|
165
|
|
|
166
|
|
|
167
|
- The construction of a 725,000-gallon long-term storage tank was
initiated in mid October, 2006 and was completed towards the end of
November, 2006.
- The circular tank has a height of 19 ft and a diameter of 81 ft.
- The walls of the cylindrical tank were constructed of heavy-duty
glass-fused steel with a cement floor.
- The project also involved the installation of a PVC pipe that connects
the NW compartment of the existing 3-day storage tank after the
effluent is conveyed from the digester.
- A pump to be used in moving the effluent to the long-term storage tank
is expected to be in place by the end of January, 1007. Once installed, the pump will provide
for conveying the effluent from the digester to the long-term storage
tank thereby eliminating the need to utilize the daily-haul method for
handling the effluent.
|
|
168
|
|
|
169
|
|
|
170
|
|
|
171
|
|
|
172
|
|
|
173
|
|
|
174
|
- The process of filling the NE side of the digester was started on the 29th
of November and completed in mid December, 2006.
- During the process, half of the collected manure was feed to the NE
side of the digester with the remaining half being feed to the SW side
of the digester that had already produced biogas for at least four
weeks.
- The effluent from the SW side of the digester was also pumped into the
NE side of the digester to provide the inoculant to startup the
anaerobic digestion process as well as fill up the NE side of the
digester as quickly as possible.
|
|
175
|
- Production of biogas started soon after the two sides of the digester
were filled with the effluent from the dairy complex.
- Biogas production became consistent starting from December 17, 2006.
- Flaring the biogas started on December 20, 2006, and went on until the
internal combustion engine/generator set was started briefly on the 9th
of January, 2007.
|
|
176
|
- Flaring the biogas continued until the interconnect with the power grid
was approved and the combined heat and power generation (CHP) system was
authorized to start on February 27, 2007.
- The system has been in operation since February 28, 2007. It has been
consistently generating electrical power close to the system’s capacity
of 50 kW since that date.
|
|
177
|
- Start the implementation of the Sampling, Testing, and Evaluation Plan
(STEP)!!
|